Relinking clips in 4.1.3

My original clip was 66 frames long. Did a few complex tracks on it and now the client needs the take to be 5 frames longer.

So I go to Clip / Footage Streams and click Relink… and select the longer shot.

After two tries the system finally relinks to the 71 frame clip BUT when I switch to the Track tab I can still see only 66 frames of material.

Must be something silly simple but I’m really stuck.

Any ideas?

TIA,
K.

Just set a new outpoint in the timeline, you should then see the extra frames.